Technical Resources

Forever Steel Manufacturing Co., Ltd
steel sewage force main,sewage pipe lining,force main pipe material

Latest news list

Steel Pipe for Sewage Force Mains: Material Comparison, Lining and H2S Corrosion Guide

Date: 2026-11-04Author:Chuck Yu

Steel is a candidate for a sewage force main when the approved design, installation and connection requirements justify a protected welded or fabricated system. Compare it with HDPE, PVC and ductile iron under the same pressure, corrosion, external-load, construction and maintenance assumptions. Large diameter or high pressure alone does not establish that steel is the preferred material.

A force main, also called a rising main in some markets, conveys wastewater under pressure from a pumping system. It differs from a gravity sewer. This guide covers material screening and purchasing requirements; it does not approve a pipe material against a local authority’s rules.

For raw water, reclaimed water or another conveyed medium, start with the Steel water pipe selection by service to identify the matching service guide and required inputs.

Common question

Short answer

Is steel used for sewage force mains?

Where the authority permits it: large diameters, high pressure, crossings and pump-station spools, with an internal lining and external protection designed for sewage.

What attacks the pipe?

Septic wastewater generates sulfides. Hydrogen sulfide released at air pockets, high points and discharge points can form sulfuric acid on wetted surfaces.

Which lining is used?

Polymer systems such as liquid epoxy or polyurethane are commonly considered; confirm the exact product against the actual wastewater.

What velocity is typical?

EPA’s fact sheet gives 0.6 to 2.4 m/s (2 to 8 ft/s) for lift-station force mains, with peaks not exceeding 3 m/s (10 ft/s).

 

steel sewage force main,sewage pipe lining,force main pipe material

Illustrative lift station and pressure main. The concept shows the buying interface between pumping equipment and pipework, not a construction design.

Force Main Pipe Material Comparison: Steel vs Ductile Iron vs HDPE vs PVC

EPA’s 2000 force-main fact sheet identifies wastewater quality, pressure, corrosion resistance and installation conditions as selection inputs, and covers surge control and cleaning. It lists cement-lined steel as suited to high pressure in all sizes with excellent surge resistance, ductile iron as the typical choice for high-pressure and exposed piping, and plastic as most common in short mains and smaller diameters. Use it for engineering background, not as a current mandatory code or evidence of today’s material market shares. US EPA Wastewater Technology Fact Sheet Sewers Force Main.

Candidate material

Questions for the project team

Quotation comparison

Protected steel

Does the owner permit the system; are fabricated details, geometry or installation conditions a reason to evaluate it

Pipe and protection; welded joints; field repair; inspection; maintenance

HDPE

Does the specific pressure pipe system meet the design and installation envelope

Product grade; dimensions; joining procedure; transitions and acceptance

PVC

Is the approved pipe and joint system suitable for the design cases and installation

Pressure basis; joint restraint where required; fittings and installation controls

Ductile iron

What internal and external protection is required for the actual wastewater and soil

Pipe class; lining; joints; protection and project approvals

 

Use equal design inputs rather than matching nominal diameter and reading the lowest price. Compare available bore, approved pressure and transient cases, joints, installation requirements and planned access. If the authority excludes steel or another candidate, settle that before commercial comparison.

When Does Steel Make Sense for a Sewage Force Main?

A steel proposal can be reviewed for engineered main sections, site-specific fabricated spools, connections and crossings where the approved design allows it. Welded joints give a restrained line and fabricated fittings can follow site geometry, but the case must still identify a concrete requirement: geometry, mating equipment, installation or fabrication scope. “Heavy duty” is not a selection criterion.

Evaluate SSAW pipe or LSAW pipe for a permitted main-line route, and ERW pipe where the required product envelope fits. Confirm seam inspection, end geometry and dimensional acceptance against the same pipe specification. Manufacture does not resolve sewage corrosion by itself.

steel sewage force main,sewage pipe lining,force main pipe material

Pipe material specimens and force-main installation considerations. No material is ranked or approved by this illustration.

Hydrogen Sulfide Corrosion in Sewage Force Mains: Assess Before You Choose a Lining

A force main runs full, but wastewater often arrives septic because dissolved oxygen is used up in the wet well. EPA notes that high points trap air, which reduces flow area and promotes sulfide corrosion, and that pump stations may aerate or chlorinate the wastewater to control odour and corrosion. In practice the worst attack is usually where sulfide can escape into a gas space and be oxidised to acid: air pockets, high points and the discharge chamber.

Obtain the actual wastewater description, relevant chemical analysis, temperature, retention time and operating information, industrial inputs and the project’s sulfide or corrosion assessment. The presence and severity of a mechanism must be evaluated for the pipeline; do not predict identical H2S exposure throughout every force main.

Internal Lining for Sewage Steel Pipe: Epoxy, Polyurethane, FBE or Cement Mortar

Northwest Pipe lists liquid epoxy (AWWA C210) and polyurethane (C222) for wastewater and sanitary force-main duty, and also lists cement mortar (C205) for force mains; Steel Mains describes different systems for different water conditions. Because cement mortar is alkaline and acid can attack it, septic duty with expected sulfide generation usually points the review towards polymer linings. These examples show that a protection system is chosen for the service; they do not approve an arbitrary epoxy, FBE or mortar product for sewage. Northwest Pipe Linings; Steel Mains Introduction to Cement Mortar Lining.

Exposure condition

Candidate systems to review

Evidence to obtain before acceptance

Acid gas-phase exposure (air pockets, high points, discharge chamber)

Polymer linings such as liquid epoxy or polyurethane; cement mortar is alkaline and acid can attack it

Product evidence for sulfide and acid exposure in the actual wastewater

Continuous full-bore immersion

Liquid epoxy, FBE or polyurethane where the supplier evidences immersion duty; mortar only where the corrosion assessment supports it

Immersion and chemical-compatibility evidence; temperature and retention conditions

Cleaning by pigging

Lining systems the supplier confirms suit the chosen pig

Pig compatibility of the lining, bends and launcher or receiver spools

Internal site joints

Repair material from the same system family

Repair procedure, cure and inspection records for that wastewater

 

Agree inspection of the shop lining and the reinstated joint as distinct stages for a liquid epoxy lined steel pipe proposal. Thickness, cure, holiday and repair records follow the pipe coating inspection guide, and the site-joint interface follows the water pipe field joint guide.

Force Main Design Interfaces: Velocity, Surge, Air Release and Pigging

Review the pressure envelope, pump start and stop cases, allowable pipe and connection loads, fittings and support details with the designer. Transmit the resulting pipework and access requirements to the supplier; do not order straight pipe while leaving those interfaces undefined.

Design item

What EPA’s fact sheet notes

What it adds to the steel pipe order

Velocity

0.6 to 2.4 m/s typical; peaks not above 3 m/s

Bore after lining; wear and scour assumptions

Surge

Surges at pump start-up and shut-off last roughly 2 to 15 seconds; critical cases can follow power failure

Approved transient pressure basis for the wall schedule

Air release

Avoid high points; use gas relief and vacuum valves where unavoidable; blowoffs at low points

Tapping, flange and valve-chamber spools

Cleaning

Pigging is the normal method for long mains; launch and retrieval stations needed

Pig-compatible lining, bends and launcher or receiver spools

 

steel sewage force main,sewage pipe lining,force main pipe material

Sewage steel-pipe inspection handoff. Pipe manufacture, shop lining, field joints and installed acceptance are separate records, connected by pipe and spool identity.

Joints, Field Repair and External Protection for Buried Steel Force Mains

A pipe-body hydrotest does not establish chemical compatibility or the integrity of every installed lining repair; keep structural testing, lining inspection and joint acceptance as separate records. Agree the site joint procedure for both surfaces, and treat external protection as its own design: a buried steel main normally needs an external coating and, where specified, cathodic protection, none of which protects the inside of the pipe.

Common Force Main Selection Mistakes

Mistake

Required correction

Steel is automatically best at large diameter

Compare all permitted materials under the same design and installation conditions

Every sewage duty needs the same H2S solution

Obtain a service-specific corrosion assessment

A normal potable-water lining is enough

Verify the proposed formulation for the actual wastewater

A pressure test proves the lining is suitable

Keep structural testing, compatibility and lining inspections separate

The comparison ends at delivered pipe price

Include joining, protection, repairs, access and maintenance assumptions

Sewage Force Main Steel Pipe RFQ Checklist

Ask Forever Steel to review a defined steel-pipe schedule, not to guarantee suitability from the words “sewage pipe”. Confirm the offered pipe route, actual protection system, inspection records and scope against the project, and identify supply-only work separately from installation and commissioning.

Item

What to include

Authority requirements

Permitted materials and standard editions

Wastewater and corrosion

Wastewater analysis; sulfide or corrosion assessment

Pump and design cases

Approved operating, pump start-stop, transient and load cases

Pipe

OD, wall and material

Protection

Lining and external protection

Spool and connection drawings

Including air-release, vacuum and valve-chamber spools

Inspection and acceptance

Inspection plan; field repair and installed acceptance

Operation and pigging access

Maintenance access; pig launcher and receiver interfaces; delivery and packing

 

FAQ: Steel Pipe for Sewage Force Mains

Is steel pipe suitable for every sewage force main?

No. The authority, wastewater exposure, approved design and installed protection system must permit it. A comparison may support another material.

Can external coating prevent internal sewage corrosion?

External coating protects the outside surface. Internal exposure requires its own compatible lining or other approved corrosion-control basis.

Is cement mortar lining suitable for sewage force mains?

It is listed by some manufacturers for force mains, but acid attack from sulfide corrosion is a concern in septic duty. Confirm suitability with the lining supplier and the project corrosion assessment.

What is the typical design velocity in a force main?

EPA’s fact sheet gives 0.6 to 2.4 m/s for lift-station force mains, and says peak velocity should not exceed 3 m/s. The project designer sets the actual value.

Can a lined steel force main be pigged?

Pigging is a standard cleaning method for force mains, so confirm that the lining, bends and launcher and receiver spools suit the chosen pig.

Is a force main the same as a gravity sewer?

No. A force main uses pressure supplied by a pumping system. A gravity sewer has a different hydraulic basis; do not transfer pipe and joint requirements without review.

Related Articles

Steel water pipe selection by service

Potable water transmission guide

Desalinated water pipeline lining guide

Slurry pipeline steel pipe and lining guide

Epoxy pipe protection

Water pipe field joint interfaces

References and Sources

US EPA Wastewater Technology Fact Sheet Sewers Force Main

Northwest Pipe Linings

Steel Mains Introduction to Cement Mortar Lining

Find what you need ?
close